The Sizewell C application was granted development consent on 20 July 2022, by the Secretary of State for Business, Energy and Industrial Strategy. SZC Co. plan for commencement and start of construction of the scheme to be in 2024, with pre-commencement works already underway.
The Council has key roles in discharging requirements, monitoring and managing the monetary mitigation contributions by SZC Co secured through a Deed of Obligation and held by the Council. Where Suffolk County Council discharges requirements, this will be published on the County Council’s Planning Register.
During the consultations and examination, Suffolk County Council has been a statutory consultee and has evaluated, challenged, and commented upon the proposals to get the best possible outcomes for the people of Suffolk.
This page provides details of key documents related to the consent and related to the examination, as well as an overview of the history of the proposals.
Further details of the proposals are available on SZC Co.’s Sizewell C pages and on the Planning Inspectorate Sizewell C website. East Suffolk Council’s website provides further detail focussed on the District Council’s responsibilities in the project.
Email sizewellc@suffolk.gov.uk.
The Development Consent Order (DCO) as made by the Secretary of State. This is the legal instrument for the consent of the proposal.
Within the DCO, requirements are set out which will be discharged either by Suffolk County Council (in relation to Highways, Public Rights of Way and Archaeology) or East Suffolk Council. Where Suffolk County Council discharges requirements, this will be published on the County Council’s Planning Register.
Suffolk County Council agreed with SZC Co and East Suffolk Council a funding package for mitigation and compensation measures for the construction and in some cases into the operational phases.
This has been agreed in a Deed of Obligation (which is the equivalent to a Section 106 agreement), which was signed by the three parties before the close of examination.
Since the signing of the Deed of Obligation, two Deeds of Variation have been signed which amend specific aspects of the original Deed.
Read:
Between April and October 2021, an Examining Authority appointed by the Planning Inspectorate held an examination into the proposals for Sizewell C.
Suffolk County Council has been a statutory consultee and has evaluated, challenged, and commented upon the proposals for a new nuclear power station to get the best possible outcomes for the people of Suffolk.
All documents submitted during the Examination by Suffolk County Council, the Applicant and other Interested Parties are published on the Planning Inspectorate website.
On 12 October 2021, Suffolk County Council submitted its Final Position Statement to the Examining Authority, at the end of the examination. Read the Final Position Statement.
In November 2009 the government announced that Sizewell, amongst other sites, would be a suitable location for a new nuclear power station.
In 2011 the National Policy Statements for Energy Infrastructure were approved. These contain the policies by which applications for major energy projects are judged, and as such, are relevant to the Sizewell proposals.
Stage | Date/timescale |
Stage One consultation: EDF Energy set out the background and context to the development | Completed on 6 February 2013 |
Stage Two consultation: a second formal stage of consultation | From 23 November 2016 to 3 February 2017 |
Stage Three consultation: a third stage of formal consultation | From 4 January 2019 to 29 March 2019 |
Stage Four consultation: a fourth stage of formal consultation, supplementary to the stage three consultation, focusing on specific issues | From 18 July 2019 to 27 September 2019 |
Submission of Development Consent Order (DCO) to the Planning Inspectorate | 27 May 2020 |
Section 56 consultation (invitation to register as an Interest Party and submit Relevant Representations to the Planning Inspectorate) | From 8 July to 30 September 2020 |
Examination of the DCO by an Examining Authority appointed by the Planning Inspectorate | 15 April to 14 October 2021 |
Decision by the Secretary of State (SoS) | 20 July 2022 |
During the examination and pre-application phases, Suffolk County Council submitted a large number of representations and commissioned several studies as supporting evidence. Key documents are included in this section.
Suffolk County Council and East Suffolk Council worked together to respond to EDF Energy’s proposals. Further information about the two councils’ work on Sizewell C including their formal joint responses to the Sizewell C pre-examination consultations are available on the joint local authority page on eastsuffolk.gov.uk.
Suffolk County Council and East Suffolk Council submitted on 12 May 2021 their joint Local Impact Report to the Planning Inspectorate, as a key examination document.
The Local Impact Report sets out the Councils’ assessment of the likely impacts of the proposed development, and considers whether the proposed mitigation is appropriate or additional mitigation is required.
The submission to the Planning Inspectorate includes also a significant number of Annexes and Appendices, which are being published on the Planning Inspectorate website.
Read the Joint Suffolk Local Impact report (PDF, 3.6MB).
In advance of the commencement of the examination, the Council submitted its Relevant Representation to the Planning Inspectorate on 28 September 2020, following a debate and decision at a meeting of the Council’s Cabinet on 22 September 2020.
The Relevant Representation provides a summary of the Council’s views on the proposals put forward in the Development Consent Order (DCO) application and identifies the key topics and issues have the Council wishes to see addressed during the examination stage.
Read Suffolk Council Council’s Relevant Representation (PDF, 513KB).
Suffolk County Council and East Suffolk Council, working closely with the Suffolk Wildlife Trust, commissioned an independent review of the bat impact assessment.
This review will inform the Councils’ discussions with EDF Energy, in order to improve the Sizewell C proposals for mitigation to ensure they will not have a significant adverse effect on bats.
Read the:
In light of Suffolk County Council’s concerns about the proposed introduction of four additional pylons and overhead lines as part of the Sizewell C proposals, and the resulting impacts on the Suffolk Coast and Heath Area of Natural Beauty (AONB), the County Council commissioned a high level independent report into the feasibility of alternative export connections avoiding pylons, to feed into the County Council’s responses to the Planning Inspectorate.
Read Sizewell C Power Export Connection review (PDF, 271KB)
Suffolk County Council commissioned an independent report into possible options to increase deliveries of materials by rail in response to the proposals put forward by EDF Energy in its Development Consent Order application, to feed into the County Council’s responses to the Planning Inspectorate.
Read the:
Following the EDF Energy Stage Two public consultation and Suffolk County Council's ask that EDF review potential alternative sites for the Accommodation Campus, the County Council commissioned an independent report as our contribution to this review.
Read the Accommodation Campus report (PDF, 4.5MB).